Estimate software development tasks accurately using various techniques. Use when planning sprints, roadmaps, or project timelines. Handles story points,…
Task Estimation
When to use this skill
Sprint Planning: Decide what work to include in the sprint
Roadmap creation: Build long-term plans
Resource planning: Estimate team size and schedule
Instructions
Step 1: Story Points (relative estimation)
Fibonacci sequence: 1, 2, 3, 5, 8, 13, 21
## Story Point guidelines
1 Point (Very Small)
Example: text change, constant value update
Time: 1-2 hours
Complexity: very low
Risk: none
2 Points (Small)
Example: simple bug fix, add logging
Time: 2-4 hours
Complexity: low
Risk: low
3 Points (Medium)
Example: simple CRUD API endpoint
Time: 4-8 hours
Complexity: medium
Risk: low
5 Points (Medium-Large)
Example: complex form implementation, auth middleware
Time: 1-2 days
Complexity: medium
Risk: medium
8 Points (Large)
Example: new feature (frontend + backend)
Time: 2-3 days
Complexity: high
Risk: medium
13 Points (Very Large)
Example: payment system integration
Time: 1 week
Complexity: very high
Risk: high
Recommended: Split into smaller tasks
21+ Points (Epic)
Required: Must be split into smaller stories
### Step 2: Planning Poker
**Process**:
1. Product Owner explains the story
2. Team asks questions
3. Everyone picks a card (1, 2, 3, 5, 8, 13)
4. Reveal simultaneously
5. Explain highest/lowest scores
6. Re-vote
7. Reach consensus
**Example**:
Story: "Users can upload a profile photo"
Member A: 3 points (simple frontend)
Member B: 5 points (image resizing needed)
Member C: 8 points (S3 upload, security considerations)
Discussion:
Use an image processing library
S3 is already set up
File size validation needed
Re-vote → consensus on 5 points
### Step 3: T-Shirt Sizing (quick estimation)
```markdown
## T-Shirt sizes
- **XS**: 1-2 Story Points (within 1 hour)
- **S**: 2-3 Story Points (half day)
- **M**: 5 Story Points (1-2 days)
- **L**: 8 Story Points (1 week)
- **XL**: 13+ Story Points (needs splitting)
**When to use**:
- Initial backlog grooming
- Rough roadmap planning
- Quick prioritization
Step 4: Consider risk and uncertainty
Estimation adjustment:
interface TaskEstimate {
baseEstimate: number; // base estimate
risk: 'low' | 'medium' | 'high';
uncertainty: number; // 0-1
finalEstimate: number; // adjusted estimate
}
function adjustEstimate(estimate: TaskEstimate): number {
let buffer = 1.0;
// risk buffer
if (estimate.risk === 'medium') buffer *= 1.3;
if (estimate.risk === 'high') buffer *= 1.5;
// uncertainty buffer
buffer *= (1 + estimate.uncertainty);
return Math.ceil(estimate.baseEstimate * buffer);
}
// Example
const task = {
baseEstimate: 5,
risk: 'medium',
uncertainty: 0.2 // 20% uncertainty
};
const final = adjustEstimate(task); // 5 * 1.3 * 1.2 = 7.8 → 8 points
Output format
Estimation document template
## Task: [Task Name]
### Description
[work description]
### Acceptance Criteria
- [ ] Criterion 1
- [ ] Criterion 2
- [ ] Criterion 3
### Estimation
- **Story Points**: 5
- **T-Shirt Size**: M
- **Estimated Time**: 1-2 days
### Breakdown
- Frontend UI: 2 points
- API Endpoint: 2 points
- Testing: 1 point
### Risks
- Uncertain API response time (medium risk)
- External library dependency (low risk)
### Dependencies
- User authentication must be completed first
### Notes
- Need to discuss design with UX team
Constraints
Required rules (MUST)
Relative estimation: Relative complexity instead of absolute time
Team consensus: Agreement from the whole team, not individuals
Use historical data: Plan based on velocity
Prohibited (MUST NOT)
Pressuring individuals: Estimates are not promises
Overly granular estimation: Split anything 13+ points
Turning estimates into deadlines: estimate ≠ commitment
Best practices
Break Down: Split big work into smaller pieces
Reference Stories: Reference similar past work
Include buffer: Prepare for the unexpected
References
Scrum Guide
Planning Poker
Story Points
Metadata
Version
Current version: 1.0.0
Last updated: 2025-01-01
Compatible platforms: Claude, ChatGPT, Gemini
Tags
#estimation #agile #story-points #planning-poker #sprint-planning #project-management
Examples
Example 1: Basic usage
Example 2: Advanced usage