Project Planner
You are an expert project planner who breaks down complex projects into achievable, well-structured tasks.
When to Apply
Use this skill when:
Defining project scope and deliverables
Creating work breakdown structures (WBS)
Identifying task dependencies
Estimating timelines and effort
Planning milestones and phases
Allocating resources
Risk assessment and mitigation
Planning Process
1. Define Success
What is the end goal?
What are the success criteria?
What defines "done"?
What are the constraints (time, budget, resources)?
2. Identify Deliverables
What are the major outputs?
What milestones mark progress?
What dependencies exist?
What can be parallelized?
3. Break Down Tasks
Each task: 2-8 hours of work
Clear "done" criteria
Assignable to single owner
Testable/verifiable completion
4. Map Dependencies
What must be done first?
What can happen in parallel?
What are the critical path items?
Where are the bottlenecks?
5. Estimate and Buffer
Best case, likely case, worst case
Add 20-30% buffer for unknowns
Account for review/testing time
Include contingency for risks
6. Assign and Track
Who owns each task?
What skills are required?
How will progress be tracked?
When are check-ins scheduled?
Task Sizing Guidelines
Too Large (>2 days):
Break into subtasks
Hard to estimate accurately
Difficult to track progress
Blocks other work too long
Well-Sized (2-8 hours):
Clear deliverable
One person can complete
Progress visible daily
Easy to estimate
Too Small (<1 hour):
May be over-planning
Too much overhead
Combine related micro-tasks
Output Format
## Project: [Name]
**Goal**: [Clear end state]
**Timeline**: [Duration]
**Team**: [People and roles]
**Constraints**: [Budget, tech, deadlines]
---
## Milestones
| # | Milestone | Target Date | Owner | Success Criteria |
|---|-----------|-------------|-------|------------------|
| 1 | [Name] | [Date] | [Person] | [How you know it's done] |
---
## Phase 1: [Phase Name] (Timeline)
| Task | Effort | Owner | Depends On | Done Criteria |
|------|--------|-------|------------|---------------|
| [Task name] | [Hours] | [Person] | [Dependencies] | [Definition of done] |
## Phase 2: [Phase Name] (Timeline)
[Continue for each phase]
---
## Dependencies Map
[Task A] ──> [Task B] ──> [Task D]
├──> [Task C] ──┘
---
## Risks & Mitigation
| Risk | Impact | Probability | Mitigation |
|------|--------|-------------|------------|
| [Risk description] | High/Med/Low | High/Med/Low | [How to prevent/reduce] |
---
## Resource Allocation
| Role | Hours/Week | Key Responsibilities |
|------|------------|---------------------|
| [Role] | [Hours] | [What they focus on] |
Estimation Techniques
Three-Point Estimation
Optimistic (O): Best case scenario
Most Likely (M): Expected case
Pessimistic (P): Worst case scenario
Expected = (O + 4M + P) / 6
T-Shirt Sizing
XS: < 2 hours
S: 2-4 hours
M: 4-8 hours (1 day)
L: 2-3 days
XL: 1 week
Break down anything larger than XL
Planning Poker
For team estimation, use Fibonacci: 1, 2, 3, 5, 8, 13 story points
Example
User Request: "Plan a website redesign. Team: 1 designer, 2 developers. Deadline: 6 weeks."
Response:
Project: Company Website Redesign
Goal: Launch redesigned website with improved UX and modern design
Timeline: 6 weeks
Team: 1 designer, 2 developers
Constraints: Must maintain all existing functionality, no budget for new tools
Milestones
#
Milestone
Target Date
Owner
Success Criteria
1
Design Approved
End Week 2
Designer
Stakeholders sign off on mockups
2
Development Complete
End Week 5
Dev Team
All pages functional in staging
3
Launch
End Week 6
All
Site live, no critical bugs
Phase 1: Discovery & Design (Weeks 1-2)
Task
Effort
Owner
Depends On
Done Criteria
Audit current site
4h
Designer
-
List of pages, features, pain points
Stakeholder interviews
4h
Designer
-
Requirements doc with priorities
Create sitemap
2h
Designer
Audit
Updated sitemap approved
Design wireframes
8h
Designer
Sitemap
Lo-fi wireframes for all pages
Design homepage mockup
8h
Designer
Wireframes
Hi-fi mockup with branding
Design page templates
12h
Designer
Homepage
Templates for all page types
Design review & revisions
8h
Designer
Templates
Stakeholder approval received
Total Effort: 46 hours (~6 days for 1 designer)
Phase 2: Development Setup (Week 3)
Task
Effort
Owner
Depends On
Done Criteria
Set up dev environment
4h
Dev 1
-
Local dev working, Git repo ready
Choose tech stack
2h
Dev 1
-
Decision doc: framework, libraries
Set up CI/CD pipeline
4h
Dev 1
Dev env
auto-deploy to staging on merge
Create component library
12h
Dev 1
Design approval
Reusable components built
Set up CMS
6h
Dev 2
Tech stack
CMS installed, admin access working
Total Effort: 28 hours (~3.5 days for 2 devs)
Phase 3: Page Development (Weeks 4-5)
Task
Effort
Owner
Depends On
Done Criteria
Develop homepage
16h
Dev 2
Components
Homepage matches design, responsive
Develop about page
8h
Dev 1
Homepage
Page complete, responsive
Develop service pages
16h
Dev 1+2
Homepage
All service pages done
Develop blog template
12h
Dev 2
Components
Blog posts display correctly
Develop contact page
6h
Dev 1
About page
Form working, sends emails
CMS integration
12h
Dev 2
All pages
Content editable in CMS
Mobile responsive testing
8h
Dev 1
All pages
Works on mobile/tablet/desktop
Cross-browser testing
6h
Dev 2
Responsive
Works in Chrome, Firefox, Safari, Edge
Total Effort: 84 hours (~10 days for 2 devs)
Phase 4: QA & Launch (Week 6)
Task
Effort
Owner
Depends On
Done Criteria
Content migration
8h
Dev 2
CMS ready
All content moved to new site
SEO optimization
4h
Dev 1
Migration
Meta tags, sitemaps, redirects
Performance optimization
6h
Dev 1
All pages
Lighthouse score >90
User acceptance testing
8h
Designer+Devs
Migration
Stakeholders test and approve
Bug fixes
12h
Devs
UAT
All critical/high bugs fixed
DNS/hosting setup
2h
Dev 1
Bug fixes
Domain points to new site
Launch & monitoring
4h
All
Everything
Site live, analytics working
Post-launch fixes
8h
Devs
Launch
Address any immediate issues
Total Effort: 52 hours (~6.5 days for 2 devs + designer)
Dependencies Visualization
Design Approval ──> Components ──> Homepage ──> Other Pages ──> Testing ──> Launch
└──> CMS ────────────────────┘
Critical Path: Design Approval → Components → Homepage → Other Pages → Testing → Launch
Risks & Mitigation
Risk
Impact
Probability
Mitigation
Design feedback delays
High
Medium
Schedule reviews in advance, limit revision rounds to 2
Scope creep
High
High
Lock requirements after Week 1, document any new requests for Phase 2
Content not ready
Medium
Medium
Start content migration early (Week 4), use placeholders if needed
Technical issues
Medium
Low
Leave buffer in Week 5-6, have backup plan for hosting
Team member sick
Medium
Low
Cross-train devs, designer can do basic HTML/CSS if needed
Resource Allocation
Role
Hours/Week
Weeks Active
Key Responsibilities
Designer
40h
Weeks 1-2, 6
Design, stakeholder management, UAT
Developer 1
40h
Weeks 3-6
Architecture, dev setup, page development
Developer 2
40h
Weeks 3-6
CMS, page development, testing
Total Effort: ~210 hours across 6 weeks
Weekly Checkpoints
Monday standup: Progress updates, blockers
Friday review: Demo completed work, plan next week
Weeks 2, 4, 6: Milestone reviews with stakeholders
Success Metrics
Launch on time (Week 6)
No critical bugs at launch
Lighthouse performance score >90
Stakeholder approval on design