Turn a plan or set of milestones into a timeline / Gantt chart. Use when asked to build a roadmap, schedule phases, show a project timeline, or visualize wha...
---
name: gantt-roadmap
description: "Turn a plan or set of milestones into a timeline / Gantt chart. Use when asked to build a roadmap, schedule phases, show a project timeline, or visualize what happens when. Produces a ready-to-render Mermaid Gantt chart (renders live, exportable as PNG/SVG) — and, because it has real dates, the result also exports to a calendar (.ics) — plus notes on the critical path and risks."
homepage: https://mohitagw15856.github.io/pm-claude-skills/skill/gantt-roadmap.html
metadata:
{
"openclaw": { "emoji": "🖼" }
}
---
# Gantt / Roadmap Skill
A list of tasks doesn't show what runs in parallel, what blocks what, or where the crunch is. A Gantt chart
does. This skill turns a plan into a **Mermaid Gantt chart** with phases (sections), dated tasks, dependencies,
and milestones — a real schedule, not a wish list. Because the output carries real dates, the playground can
also export it straight to a calendar (`.ics`).
## Required Inputs
Ask for these only if they aren't already provided:
- **The work** — phases and tasks to schedule.
- **Timing** — a start date, and durations or end dates (or relative ordering you can date from the start).
- **Dependencies** — what must finish before what can start.
- **Milestones** — the dated checkpoints (kickoff, beta, GA, launch).
If exact dates aren't given, anchor to a start date and lay tasks out by stated duration/order; flag the dates as planning estimates.
## Output Format
### [Project] — roadmap
One line on the time span and goal.
```mermaid
gantt
title [Project] roadmap
dateFormat YYYY-MM-DD
axisFormat %b %d
section Discovery
Research :done, r1, 2026-07-01, 10d
Spec sign-off :milestone, m1, 2026-07-15, 0d
section Build
Core build :active, b1, after m1, 20d
Integrations : b2, after b1, 10d
section Launch
Beta :milestone, m2, 2026-08-25, 0d
GA :milestone, m3, 2026-09-10, 0d
```
**Critical path** — the chain of dependent tasks that sets the end date.
**Risks / buffers** — where the schedule is tight, what could slip, where buffer exists.
**Assumptions** — any dates you estimated rather than were given.
## Mermaid Rules (so it renders)
- Start with `gantt`, then `title`, `dateFormat YYYY-MM-DD`, optional `axisFormat`.
- Group with `section Name`. Task line: `Label : [status,] id, start, duration` (e.g. `:active, b1, 2026-07-01, 20d`).
- Dependencies use `after <id>` as the start. Milestones use the `milestone` tag with `0d`.
- Use real ISO dates (`YYYY-MM-DD`) so the calendar (.ics) export works.
## Quality Checks
- [ ] Tasks are grouped into phases (sections) and have real start dates/durations
- [ ] Dependencies use `after` so the schedule reflects what blocks what
- [ ] Milestones are marked as milestones, not full-width bars
- [ ] The critical path is identified, with risks/buffers noted
- [ ] The Mermaid block renders, and dates are ISO so .ics export works
## Anti-Patterns
- [ ] Do not list tasks with no dates or durations — that's a checklist, not a timeline
- [ ] Do not ignore dependencies — overlapping things that can't overlap is a fake plan
- [ ] Do not draw milestones as long bars — they're points in time
- [ ] Do not use ambiguous date formats — stick to `YYYY-MM-DD`
- [ ] Do not present estimated dates as commitments — flag assumptions
## Based On
Project scheduling (Gantt charts, critical path, milestones, dependencies), expressed as renderable Mermaid.